Time and cost trade-offs between overtime and workforce expansion for remaining structural work in a building project in Bali
Schedule acceleration requires comparing additional resource costs with time-dependent overhead savings. This quantitative case study evaluates overtime and workforce expansion for remaining structural work in the XYZ Tabanan building project, Bali, Indonesia. A Microsoft Project precedence network and Microsoft Excel...