Predicting Schedule Delays and Cost Overruns in Iraqi Road and Bridge Projects Using Statistical Analysis and Explainable Artificial Intelligence

Sep 2026 · Bilad Alrafidain Journal for Engineering Science and Technology · Vol 5, pp. 194-213 · 0 citations · 64 references

TL;DR

An integrated framework that combines statistical analysis, machine learning, and explainable artificial intelligence to identify, rank, and model project-risk factors in Iraqi transport infrastructure supports transparent early-warning assessment of financial, procurement, design, site, and management risks.

Abstract

Schedule delays and cost overruns remain persistent challenges in Iraqi road and bridge projects. This study presents an integrated framework that combines statistical analysis, machine learning, and explainable artificial intelligence to identify, rank, and model project-risk factors. The study uses a structured questionnaire with clients, consultants, contractors, project managers, planning engineers, cost-control personnel, and site engineers. At the same time, project-level records provide schedule, cost, variation, payment, design, procurement, and site variables. The analytical workflow includes descriptive statistics, the Relative Importance Index, Cronbach's alpha, exploratory factor analysis, correlation, group-comparison tests, regression, and machine-learning models including Ridge, LASSO, Decision Tree, Random Forest, XGBoost, Support Vector Regression, and a compact neural network. We evaluate predictive performance using MAE, RMSE, and R², with classification metrics where relevant, and use SHAP to support model interpretation. The numerical project and model results currently embedded in the manuscript are illustrative simulated outputs retained to demonstrate the proposed workflow. They must be replaced with verified project-level data before reporting empirical conclusions. The framework supports transparent early-warning assessment of financial, procurement, design, site, and management risks in Iraqi transport infrastructure

Read PDF

Similar papers

Review Sep 2026

AI METHODS FOR COST OVERRUNS AND DELAYS FORECASTING

Cost overruns and delays remain persistent challenges in construction projects. Traditional estimation methods struggle to capture uncertainty and nonlinear interactions among risk factors, leading the industry to adopt artificial intelligence (AI) for predictive management. In this study, a systematic literature revie...

Lucia-Gabriela Chávez-Quiroga, T. García-Segura, Begoña Moreno-Escobar et al. · 0 citations
Open access Aug 2026

Mitigating Schedule and Cost Overrun Risks in EPC Projects Using Monte Carlo Simulation in Ikeja

Engineering, Procurement and Construction (EPC) projects play a pivotal role in infrastructure and industrial development in Nigeria but continue to experience significant schedule delays and cost overruns arising from engineering complexity, procurement uncertainty, macroeconomic volatility, and regulatory constraints...

A. Adeodu, T. Ojo, Margaret Emmen Ogunbiyi · 0 citations
Conference Open access 2026

Development of a Predictive Analytics-Driven Decision Support System for Smart Construction Schedule Control

Schedule delays remain a recurring concern in Philippine vertical construction projects. In the projects examined, delays were associated with design revisions, vendor-related problems, procurement activities, site conditions, and external factors such as adverse weather. Conventional project monitoring methods are lar...

Jia Marella Del Rosario, Dante L. Silva · 0 citations
Sep 2026

MACHINE LEARNING MODEL FOR ESTIMATING THE COST OVERRUN OF PROCUREMENT MATERIALS IN CONSTRUCTION PROJECTS

Procurement is a critical phase in construction projects, where inaccurate cost estimation can lead to significant cost overruns and reduced project efficiency. This study proposes a machine learning model based on an Artificial Neural Network (ANN) to predict procurement material cost overruns and identify the factors...

A. Mohammed · 0 citations
Open access Sep 2026

Machine Learning-Based Prediction of Construction Project Costs and Overruns Using a Comparative Study of Benchmark Datasets

The findings indicate that gradient-boosted ensembles are the most robust default for heterogeneous construction data, and that machine learning can already serve as an effective delay-triage tool using routinely archived administrative records — a practice directly transferable to public project governance in developi...

Mustafa Al-Saadi · 0 citations

We use cookies to run the site and, with your consent, for analytics and to show ads. See our Cookie Policy.