Short-Term Peak-Shaving Dispatch for Cascade Hydropower Based on Load Curve Reconstruction

Oct 2026 · Water · Vol 18, pp. 2541 · 0 citations · 45 references

Abstract

The increasing integration of variable renewable energy (VRE) into power grids has significantly widened the peak-to-valley difference in net load and intensified its volatility. To follow these rapid load changes, cascade hydropower plants must frequently adjust their output, operate within unstable oscillation zones, or undergo repeated start-stop cycles. This creates a growing conflict between the system’s demand for peak shaving and the actual operational capabilities of hydropower plants. To address this challenge, this paper proposes a method for reconstructing the load curve based on fuzzy recognition of peak-valley characteristics. By adaptively adjusting the number of identified features, the method transforms the highly fluctuating net load into a multi-segment linear form. This preserves essential peak and valley information while promoting output stability. Building on this reconstructed load curve, a short-term peak-shaving model for cascade hydropower is developed, aiming to minimize the standard deviation of the residual load. The model is solved using an improved progressive optimality algorithm (POA) that integrates feasible region reduction with a multi-segment, variable-step-size search strategy. The peak-shaving performance is evaluated under three VRE penetration scenarios: low (10%), medium (20%), and high (40%). A case study conducted on China’s Wujiang River demonstrates the effectiveness of the proposed method. The load curve reconstruction transforms hydropower output from hourly sawtooth-like fluctuations into a stepwise pattern, albeit with a slight reduction in the peak-to-valley difference optimization rate (PVOR). For example, in the 10% penetration scenario, the frequency of output adjustments decreases by 73.2%. As the VRE penetration rate increases, the net peak-to-valley load difference grows sharply, and the PVOR of the reconstruction scheme declines from 26.70% to 9.12%. Nevertheless, the frequency of output adjustments does not exceed 15 times, thereby maintaining stable operation. The proposed approach achieves a reasonable trade-off between peak-shaving effectiveness and operational stability, offering a practical solution for hydropower dispatch in grids with high VRE penetration rates.

Read PDF

Similar papers

Open access Oct 2026

Research on Multi-Time-Scale Optimal Scheduling of Hydro–Solar Complementation in the Shuoqu River Basin

The integration of high shares of renewable energy into the power grid poses significant challenges to the stable operation of power systems. Hydropower, owing to its rapid response capability and reservoir regulation capacity, can effectively mitigate the volatility and randomness associated with photovoltaic power ou...

Dong-Yang He, Qing-Yan Yang, Yu-Jie Gao et al. · 0 citations
Open access Oct 2026

Stored-Energy-Based Operation Rules for Cascaded Hydropower to Support High-Renewable Integration

High wind and photovoltaic (PV) penetration reshapes intra-annual residual energy demand and changes hydropower generation space and operating patterns. Conventional medium- to long-term scheduling methods struggle to coordinate renewable-energy integration, supply reliability, and seasonal hydropower utilization. This...

Tian-Cai Zuo, Rong Huang, Jiang-Long Zhu et al. · 0 citations
Conference Open access Sep 2026

Short-term peak-shaving scheduling of a cascade hydro-wind-PV-pumped storage system considering cumulative forecast deviations

The high penetration of wind and photovoltaic (PV) power increases the peak-shaving pressure on the power grid, while limited forecast accuracy lets wind-PV deviations accumulate over consecutive dispatch periods. Neglecting these cumulative deviations in scheduling may leave the allocated electricity reserve insuffici...

Ju-Long Chen, Zhen Li, Bin Wang et al. · 0 citations
Conference Sep 2026

Dynamic division method of virtual power plant based on the improvement of renewable energy consumption capacity

Large-scale wind and photovoltaic integration can reduce fossil-fuel consumption, but renewable output uncertainty and anti-peak-regulation characteristics increase curtailment, dispatch complexity and ancillary-service costs. To improve renewable energy accommodation, this paper proposes a dynamic virtual power plant...

Jian-Li Zhu, Zhi-Yun Hu, Hong-Lian Zhou et al. · 0 citations
Open access 2026

Short-Term Electric Load Forecasting by Cross-Feature Analysis and Multimodal Selection

The proposed short-term coupled forecasting model of power loads based on AI technology demonstrates high accuracy and robustness across different time scales and is helpful for the power industry to better cope with power market fluctuations and changes.

Li-Ling Peng, Tong Li, Guo-Feng Fan et al. · 0 citations
Open access 2026

Three-Stage Model to Solve the Transmission Expansion Planning and Reactive Power Supply Under Wind Generation Uncertainty

The high penetration of renewable energy is an important characteristic of modern power systems. However, the inherent intermittency nature of these sources leads to significant challenges in grid planning. In this way, this paper proposes an innovative three-stage model (TSM) to optimize both transmission expansion pl...

C. Moraes, L. S. Nepomuceno, A. N. de Paula et al. · 0 citations

We use cookies to run the site and, with your consent, for analytics and to show ads. See our Cookie Policy.