Assessing the Determinants of Effective Force Account Implementation in Public Road Construction Projects in Tanzania

2026 · Journal of Policy and Development Studies · 0 citations

Abstract

This study assessed the determinants of effective Force Account implementation in public road construction projects in Tanzania. The study adopted a cross-sectional research design whereas primary data were collected through structured questionnaires from 120 respondents working on Force Account road construction projects in Ilala, Temeke, and Kinondoni districts of Dar es Salaam. Data were analyzed using descriptive statistics, reliability and validity tests, correlation analysis, and hierarchical multiple regression based on the Ordinary Least Squares (OLS) estimation technique. The findings revealed that all four principal determinants significantly and positively influenced Effective Force Account Implementation, with Procurement and Project Management Practices exerting the strongest effect (β = 0.326, p < 0.001), followed by Institutional Capacity (β = 0.267, p < 0.001), Financial Capacity (β = 0.214, p < 0.001), and Resource Availability (β = 0.186, p = 0.002). Regarding the control variables, different levels of working experience, education and job position exhibited significantly higher perceptions of Effective Force Account Implementation than their respective reference categories, while the remaining control variables were not statistically significant. The study recommends strengthening institutional and technical capacity, ensuring timely financing of projects, improving procurement planning and supply chain coordination, investing in construction equipment and skilled personnel, and enhancing monitoring and evaluation mechanisms to improve the efficiency, quality, and sustainability of Force Account road construction projects in Tanzania.  

Read PDF

Similar papers

Open access Sep 2026

Examining the Correlation of Critical Factors for Effective Quality Control Performance in TARURA Road Infrastructure Projects

This study examines the interrelationships among key determinants of quality control performance in road infrastructure projects implemented under the Tanzania Rural and Urban Roads Agency. The quantitative approach was adopted, and data analysed using the SPSS package was used together with the Principal Compone...

Dickson Lukanazya, R. Tekka, Japhari Shengeza · 0 citations
Open access Sep 2026

Analysis of the Determinants of Cost Overruns in Road Construction Projects in Tanzania: A Probit Regression Model Approach

Road construction projects in Tanzania continue to experience persistent cost overruns, undermining infrastructure development and broader economic growth. This study employs probit regression analysis to identify the key factors influencing cost escalation in road construction projects. The main objective was to deter...

F. A. Rwechungura · 0 citations
Review Open access Sep 2026

Influence of Cooperative Procurement Procedures on Cost Performance of Building Projects in Borno State, Nigeria

Public procurement plays a critical role in construction project delivery; however, persistent cost overruns in Nigeria highlight inefficiencies in traditional procurement systems. This study, therefore, aimed to assess the influence of cooperative procurement procedures on the cost performance of building projects...

Ashgar Ahmed Shettima · 0 citations
Review Open access Aug 2026

Procurement Planning on Public Service Delivery in Local Governments: Evidence from a Structural Equation Modelling Analysis

Purpose: This study examined the effect of procurement planning on public service delivery in local governments. Specifically, the study investigated the effect of needs identification, market assessment, and procurement scheduling on public service delivery. Methodology: The study adopted a quantitative research appr...

Gerald Muheesi, Sunday Arthur, Eton Marus et al. · 0 citations
Review Open access Aug 2026

Assessment of Inventory Management Factors Affecting Construction Project Delivery in Imo State, Nigeria

This study examined the assessment of inventory management factors affecting construction project delivery in Imo state, Nigeria. Adopting a descriptive survey research design. The study population comprised 800 construction professionals, including architects, estate surveyors and valuers, site engineers, materials pu...

Unknown authors · 0 citations
Review Open access Sep 2026

Critical Factors Affecting Labour Productivity: Evidence from Construction Industry

Labour productivity significantly influences the cost, time, and overall success of construction projects. This study identifies and analyses critical factors affecting labour productivity in building construction projects in the Central Gujarat region, India. An extensive literature review initially identified 66 fact...

Megha Desai, V. Panchal, R. Bhatt · 0 citations

We use cookies to run the site and, with your consent, for analytics and to show ads. See our Cookie Policy.