Analysis of the Determinants of Cost Overruns in Road Construction Projects in Tanzania: A Probit Regression Model Approach

Sep 2026 · Journal of Sustainable Research and Development · Vol 2, pp. 1-13 · 0 citations

Abstract

Road construction projects in Tanzania continue to experience persistent cost overruns, undermining infrastructure development and broader economic growth. This study employs probit regression analysis to identify the key factors influencing cost escalation in road construction projects. The main objective was to determine the determinants of cost overruns by examining seven categories of influences: client-related, consultant-related, contractor-related, project-related, government-related, managerial, and economic factors. The study focused on major road sector stakeholders, including contractors, consultants, and clients affiliated with TANROADS and TARURA. A cross-sectional research design was adopted, with primary data collected from 200 respondents using stratified and simple random sampling techniques. The final sample comprised 100 contractors, 50 clients, and 50 consultants. A total of 179 valid responses were obtained, representing a 89.5% response rate. Respondents were senior professionals with substantial industry experience, and the sampling frame was drawn from the Contractors Registration Board (CRB) database. Probit regression results indicate strong overall model performance, with a likelihood ratio chi-square statistic of 66.16 (p < 0.0001) and a pseudo-R² of 0.3179. Consultant-related factors (dy/dx = 0.8091, p < 0.001) and managerial inefficiencies (dy/dx = 0.7834, p < 0.001) were found to significantly increase the probability of cost overruns. Client involvement also exhibited a notable effect (dy/dx = -0.3705, p = 0.079). In contrast, government-related factors demonstrated a significant negative association with cost overruns (dy/dx = -0.5259, p < 0.001), suggesting the effectiveness of recent reform initiatives. Project-related, contractor-related, and economic factors were not statistically significant. The study concludes that improving consultant performance, strengthening managerial capacity, and enhancing governance mechanisms are critical for effective cost control in Tanzania’s road sector. This study contributes to the existing body of knowledge by providing empirical evidence on the relative importance of consultant-related, managerial, client-related, and government-related factors in explaining cost overruns in Tanzanian road construction projects. Unlike many previous studies that relied primarily on descriptive analyses, the study employs a probit regression approach to quantify the probability effects of different determinants, thereby offering context-specific insights for infrastructure policy and project management in Tanzania.

Read PDF

Similar papers

Review Open access Sep 2026

Investigating Major Factors Contributing to Construction Project Cost Overruns: A Structural Equation Modeling Approach

A greater demand is placed on stakeholders to deliver projects on time and within budget. This study examines the prevalence and underlying causes of cost overruns in Saudi Arabian construction projects and models the interrelationships among those causes. Twenty-five factors were identified from the literature and ref...

K. Aldossari · 0 citations
Conference Open access 2022

Project risk factors leading to construction cost overruns

Most of the construction projects fail to be completed within cost and time. This study aimed to assess the project risk factors that lead to construction cost overruns. The study employed a quantitative research approach. A purposive sampling technique was used to source data from a sample size of 50 respondents. A su...

M. Tshehla · 0 citations
Review Open access Oct 2026

Explaining and comparing delay patterns in urban construction projects across government and non-government sectors in Tabriz

Construction project delays remain a critical challenge in urban developent, particularly in contexts characterized by financial constraints, institutional complexity, and fragmented stakeholder responsibilities. This study investigates the key causes of delays in urban construction projects through a comparative analy...

Ali Zamanfar, Hooman Sobouti · 0 citations
2026

An Empirical Assessment of Delay Factors in Road Maintenance Projects Using PLS-SEM

This study empirically examines the determinants of time overrun in road maintenance projects in North Central Nigeria, using Partial Least Squares Structural Equation Modeling (PLS-SEM) to analyze interrelationships among multiple latent constructs. Data were collected via structured questionnaires from project manage...

S. Ajayi, Abdulrahman Shuaibu · 0 citations
Open access Sep 2026

Influence of Client-Related Variations on Implementation of Kenya National Highways Authority Projects

Client‑related variations such as scope changes, specification modifications, delayed instructions, and financial constraints are a major source of delays and cost overruns in infrastructure projects. Globally, they account for 6-15% of cost escalations in Europe and up to 45% of schedule slippages in Asia. In Africa,...

Francis Benedict Ondiek, Antony Sije, Yusuf Muchelule · 0 citations
Open access 2026

Assessing the Determinants of Effective Force Account Implementation in Public Road Construction Projects in Tanzania

This study assessed the determinants of effective Force Account implementation in public road construction projects in Tanzania. The study adopted a cross-sectional research design whereas primary data were collected through structured questionnaires from 120 respondents working on Force Account road construction proje...

Makawa Laurent · 0 citations

We use cookies to run the site and, with your consent, for analytics and to show ads. See our Cookie Policy.