From prediction to decision support: explainable machine learning for schedule-delay risk in complex infrastructure projects

Jul 2026 · Journal of Engineering, Design and Technology · pp. 1-25 · 0 citations · 28 references

TL;DR

The explainability analysis indicates that predicted schedule-delay risk is associated with non-linear, model-attributed risk-state patterns rather than isolated variables, and the framework can support more transparent and accountable infrastructure project governance.

Abstract

Schedule delay remains a persistent challenge in large-scale infrastructure programmes, yet many predictive studies prioritise model accuracy while offering limited support for managerial interpretation and decision-making. This study aims to develop and evaluate a case-grounded, explainable hybrid machine-learning framework for schedule-delay risk prediction and decision-support translation. The study integrates random forest and support vector machine within a weighted ensemble, with genetic algorithm optimisation applied to the random forest configuration. Shapley additive explanations is used to interpret model-attributed predictive contributions and identify non-linear risk-state patterns. The framework uses 470 case-grounded, programme-level risk-state observations derived from screened expert assessments and cross-checked against project documentation, practitioner interviews and schedule records. The random forest-genetic algorithm + support vector machine model produced strong predictive results within the studied data set, achieving 92.2% accuracy with balanced precision, recall and F1-score values. The explainability analysis indicates that predicted schedule-delay risk is associated with non-linear, model-attributed risk-state patterns rather than isolated variables. Material and equipment supply, contractor performance and design changes emerged as the most salient predictive signals. These signals represent model-attributed contributions to predicted delay probability, not causal effects. The study is based on a single large-scale infrastructure programme; therefore, broader transferability requires validation across multiple programmes, delivery systems and national contexts. The data are partly expert-informed, although screened and cross-checked against documentary and schedule evidence. SHAP-based explanations are model-attributed and should not be interpreted as causal effects. Future research should examine temporal modelling and benchmarking against XGBoost, LightGBM, CatBoost and deep-learning approaches. The framework supports structured managerial prioritisation by translating model outputs into operational risk bands, trigger conditions, responsible actors, intervention timing and measurable outcomes. By translating delay-risk predictions into explainable and trigger-based decision-support actions, the framework can support more transparent and accountable infrastructure project governance. Earlier identification of schedule-risk conditions may help reduce avoidable delays, resource waste, contractual disputes and disruption to public-service delivery. In large infrastructure projects, improved schedule-risk management can contribute to more reliable delivery of assets that affect communities, economic activity and public-sector investment efficiency. However, the framework should support, not replace, professional judgement and stakeholder accountability. The study contributes by integrating hybrid prediction, explainable artificial intelligence and operational decision-support translation within a case-grounded infrastructure programme context. Rather than treating predictive accuracy or SHAP rankings as final outputs, the framework links predicted delay probability, dominant model-attributed risk signals and operational domains to trigger-based decision support.

View source

Similar papers

Open access Sep 2026

Machine Learning-Based Prediction of Construction Project Costs and Overruns Using a Comparative Study of Benchmark Datasets

The findings indicate that gradient-boosted ensembles are the most robust default for heterogeneous construction data, and that machine learning can already serve as an effective delay-triage tool using routinely archived administrative records — a practice directly transferable to public project governance in developi...

Mustafa Al-Saadi · 0 citations
Open access Aug 2026

Machine Learning–Driven Classification Model to Support Study Assignment Decisions under the Study-on-Mission Program at PT X

This study evaluates the efficacy of machine learning as a decision support instrument for mission assignment at PT X, grounded in empirical model performance and data attributes, indicating that machine learning models are more efficacious when utilized as decision support systems instead of automated decision-makers.

Annisa Putri Permatasari, I. Yuadi · 0 citations
Open access Sep 2026

A data-driven decision-support framework for predictive quality management in FMCG manufacturing

Quality management in high-volume manufacturing increasingly requires data-driven approaches that complement conventional retrospective analysis. This study developed a retrospective decision-support framework for FMCG biscuit manufacturing by integrating Six Sigma DMAIC with regression modelling, time-series forecasti...

S. Hakim, Galuh Zuhria Kautzar, Andy Hardianto et al. · 0 citations
Review Open access 2026

Explainable machine learning for predicting cost and schedule overruns in irrigation projects: A safety-driven approach

Irrigation projects are essential for ensuring water security and sustainable agricultural development; however, they are highly susceptible to human, managerial, equipment, and environmental risks that contribute to cost overruns and schedule delays. Although machine learning (ML) has been widely applied to project pe...

Abbas Ali, Hatim Abd Al-Karim · 0 citations
Sep 2026

A machine learning-driven approach to optimizing maintenance scheduling for industrial machinery

An integrated framework combining supervised machine learning classification with mathematical optimization to predict equipment failures and minimise maintenance costs under prediction uncertainty is developed, ensuring prediction uncertainty propagates into scheduling decisions and bridging predictive analytics with...

Nooshin Salehabadi, Ming-Yuan Chen · 0 citations
Open access Sep 2026

Predicting Schedule Delays and Cost Overruns in Iraqi Road and Bridge Projects Using Statistical Analysis and Explainable Artificial Intelligence

An integrated framework that combines statistical analysis, machine learning, and explainable artificial intelligence to identify, rank, and model project-risk factors in Iraqi transport infrastructure supports transparent early-warning assessment of financial, procurement, design, site, and management risks.

Enass Mohammed · 0 citations

We use cookies to run the site and, with your consent, for analytics and to show ads. See our Cookie Policy.