Risk-Based Time Contingency Analysis for Hospital Building Construction Projects Using the Pert (Program Evaluation and Review Technique) Method

Aug 2026 · Journal of social research · Vol 5, pp. 4714-4729 · 0 citations · 25 references

TL;DR

The findings demonstrated that risk-based PERT provides a more realistic and adaptive scheduling framework for mitigating delay risks in complex hospital construction projects.

Abstract

Hospital construction projects involve high technical complexity, multidisciplinary coordination, and uncertainty, which can increase the risk of schedule delays. This study aimed to develop a risk-based time contingency analysis using the Program Evaluation and Review Technique (PERT) to improve schedule reliability for the Central Medical Building project at HVA Toeloengredjo Hospital, Kediri. This applied quantitative study used primary data obtained from interviews, questionnaires, and observations, supported by secondary data, including the work breakdown structure, project schedules, cost plans, and progress reports. Optimistic, most likely, and pessimistic activity durations were validated by experts, while activity relationships and critical paths were analyzed using the Precedence Diagram Method (PDM) and PERT. The results showed that the existing deterministic schedule of 335 days had only a 10.34% probability of timely completion, whereas PERT estimated an expected project duration of 356.17 days with a standard deviation of 16.77 days. Architectural, reinforced concrete, plumbing, medical gas, and water utility works contributed significantly to schedule uncertainty. Achieving completion probabilities of 80% and 90% required approximately 14 and 21 additional contingency days, resulting in total project durations of approximately 370 and 378 days, respectively. The findings demonstrated that risk-based PERT provides a more realistic and adaptive scheduling framework for mitigating delay risks in complex hospital construction projects.

Read PDF

Similar papers

Open access Sep 2026

A Study on The Influence of Building Construction Project Delays Besed on Delay Factors using The Analytic Hierarchy Process (AHP) and Simple Additive Weighting (SAW) Methods in West Nusa Tenggara Province

Building construction projects involve various complex stages, ranging from planning and material procurement to execution and quality control. This complexity requires effective and efficient project management to ensure that projects are completed according to the established schedule, quality standards, and budget....

Dewi Komala, Buan Fajri, N. Ngudiyono · 0 citations
Review Open access Aug 2026

Application of Network Analysis in Improving Project Management Using Project Evaluation and Review Techniques.

This study investigates the application of the Project Evaluation and Review Technique (PERT) in improving project management performance using the construction of the Technology Park at the Federal University of Technology (FUT), Minna, as a case study. Secondary data comprising project activities, precedence relation...

Umar Ahmed, N. Nyor, Yusuf Shakirudeen · 0 citations
Review Open access Sep 2026

Project Time Scheduling Evaluation Using CPM and PERT Methods: A Case Study of New Store Concept Development

Project delays remain a major challenge in retail development projects, particularly when project planning relies on conventional scheduling approaches that fail to capture activity interdependencies and uncertainty. This study aims to evaluate project scheduling performance in the New Store Concept Development project...

Wildan Karim Anggaperbata, Ahmad Hidayat Sutawidajaya · 0 citations
Review Open access Aug 2026

Risk-Based Contingency Cost Analysis Using the Expected Monetary Value Method

Construction projects are characterized by high levels of uncertainty that may affect project cost, quality, and schedule performance. Effective risk management is therefore essential to determine contingency costs that adequately reflect project risks. This study aims to identify dominant construction work packages ba...

Ni Luh Ayu Ariati, Dewa Ketut Sudarsana, G.A.P. Candra Dharmayanti · 0 citations
Conference Open access 2026

Early Detection of Construction Project Delays: A Comparative Case Study of Earned Value, Earned Schedule, and Earned Duration Methods on a Building Project at Surabaya

Construction project delays can adversely affect cost, productivity, and timely completion. This study compares the performance of the Earned Value Method (EVM), Earned Schedule Method (ESM), and Earned Duration Method (EDM) in detecting schedule delays in the Educational Building Project at Universitas Negeri Surabaya...

Gde Agus Yudha Prawira Adistana, M. F. Sofianto, Wahyu Dwi Mulyono et al. · 0 citations
#artificial intelligence Review Open access Sep 2026

Integrated Time–Cost–Risk Management in Industrial Construction: A Systematic Review and Unified Analytical Taxonomy

Industrial construction projects involve complex interactions among uncertainty, risk, schedule, and cost, motivating the development of advanced analytical and decision-support methodologies. This study systematically reviews methodological approaches to risk assessment and performance management in industrial constru...

Cemil Turan, Maksat Kalybek, Aigul Zhasmukhambetova et al. · 0 citations

We use cookies to run the site and, with your consent, for analytics and to show ads. See our Cookie Policy.