Integration of Cost of Quality and Risk Analysis to Reduce Failure Costs in the KIIC Margakarya 150 KV Substation Civil Engineering Project

Aug 2026 · Journal Research of Social Science Economics and Management · 0 citations

Abstract

Quality failures in construction projects increase costs through failure costs, which are primarily driven by project implementation risks. Quality cost management and risk management are often conducted separately, resulting in limited integration for decision-making, particularly in civil construction projects within the electricity sector. This study aimed to identify risks contributing to failure costs, determine priority risks based on Risk Exposure and Expected Monetary Value (EMV), identify appropriate risk response strategies, and evaluate the effect of integrating risk mitigation into Cost of Quality (CoQ) management on reducing potential failure costs. This research employed a case study approach focusing on the civil works of the 150 kV KIIC Margakarya Substation Project. Data were obtained from project documents, quality reports, quality cost records, and expert judgments from eight experts. The analysis included CoQ classification using the prevention–appraisal–failure model, risk event identification based on the Risk Breakdown Structure (RBS), Risk Exposure assessment, EMV calculation, evaluation of mitigation effectiveness and costs, and calculation of residual EMV and projected post-mitigation CoQ. The total actual CoQ was IDR 259,861,400. Thirteen risk events were identified, with five priority risks categorized as high and very high, representing a total EMV of IDR 342,500,000. The selected mitigation strategies reduced the residual EMV to IDR 117,910,000, representing a 65.57% reduction. By integrating mitigation costs of IDR 72,000,000, the projected CoQ was reduced from IDR 602,361,400 to IDR 449,771,400, resulting in potential savings of IDR 152,590,000 (25.33%) and a benefit-to-cost ratio of 3.12.

Read PDF

Similar papers

Review Open access Aug 2026

Risk-Based Contingency Cost Analysis Using the Expected Monetary Value Method

Construction projects are characterized by high levels of uncertainty that may affect project cost, quality, and schedule performance. Effective risk management is therefore essential to determine contingency costs that adequately reflect project risks. This study aims to identify dominant construction work packages ba...

Ni Luh Ayu Ariati, Dewa Ketut Sudarsana, G.A.P. Candra Dharmayanti · 0 citations
Open access Aug 2026

Empirical Analysis of Time-Cost Risk Coupling in Construction Projects using FMEA, Correlation, and Regression Models

Construction project time and cost overruns continue to pose a significant performance challenge, hindering financial viability, delivery certainty, and stakeholder confidence. Although time and cost overruns are common, treating them as separate issues often diminishes the effectiveness of risk mitigation strategies....

Diksha Sanjay Jadhav, A. Katdare · 0 citations
Open access Aug 2026

Risk Management Analysis in the Implementation of the Mataram Mayor's Office Development Project

In the implementation of construction projects, particularly the Mataram Mayor's Office Development Project, various risks may lead to cost overruns, delays in project completion, and reduced work quality. During the construction phase, contractors face various uncertainties; therefore, effective risk management is req...

Anang Aprillah, N. Ngudiyono, M. Mahendra · 0 citations
Open access Aug 2026

Contractual Governance of Cost Risk Allocation in Power Engineering Projects under the EPC (Engineering, Procurement, and Construction) Contracting Model

Cost risk allocation remains a key challenge in EPC-mode power engineering projects, where technical, market, and operational uncertainties can affect project delivery and lifecycle costs. This study investigates contractual governance mechanisms for optimizing cost risk distribution, using the DART (Definability, Affo...

W.-W. Wang, Y.-L. Zhuang · 0 citations
Conference

Using Risk Analysis to Optimize Engineering Economy

The Engineering Economy of a project plays an important role in determining the overall success of the company or group involved. Project risks may affect the budget, schedule, performance, quality, or safety aspects of the project or system. These risks could mean the difference between a company’s economic stability...

Ethan Croucher · 0 citations

We use cookies to run the site and, with your consent, for analytics and to show ads. See our Cookie Policy.